Guide to pressure calculation for electrical installations with rated voltages above 1 kV AC and their installation rooms in the event of an arc fault
Class/Status:
Draft,
valid
Released: 2024 -06 Published:
2024-05 -31
VDE Art. No.: 1100847
End of objection deadline:
2024-09-30
This guideline describes the principles and procedures for calculating the pressure rise in switchgear assemblies with rated voltages greater than 1 kV AC and their installation rooms in case of an arc fault. In accordance with the requirements of DIN EN 61936-1, the mechanical load on the building construction caused by the internal pressure rise due to an arc fault must be taken into account when planning installation rooms.
This Document is related to the following Topics (in bold):
Elektrische Anlagen und Betriebsmittel auf Baustellen; Erläuterungen zu DIN VDE 0100-410 Schutzmaßnahmen – Schutz gegen elektrischen Schlag, DIN VDE 0100-704 Anforderungen für Betriebsstätten, Räume und Anlagen besonderer Art – Baustellen, DIN EN 61439-4 (VDE 0660-600-4) Baustromverteiler (BV), DGUV-Information 203-006 Auswahl und Betrieb elektrischer Anlagen und Betriebsmittel auf Bau- und Montagestellen sowie weiterer Normen und DGUV-Vorschriften/Unfallverhütungsvorschriften (UVV) VDE-Schriftenreihe – Normen verständlich, Band 142
2024, 274 pages, Din A5, Broschur
Dieser Buchtitel ist auch als E-Book (PDF) erhältlich
We use cookies on our website. Some are necessary, while others help us to improve website performance
and are used to provide personalized advertising.
For more information, please see our
data protection policy.
Individual Cookie Settings
Necessary Cookies
cookie_consent (Validity: 1 year)
PHPSESSID (Temporary, is removed when the browser is closed)
Optional Cookies
_gcl_au (Validity: 90 days)
_uetvid (validity: 30 days) - Stores a unique visitor ID for tracking user interactions.
_uetsid (validity: 30 minutes) - Saves a session ID for tracking the current visitor session.