Comparison and optimization of transmission line tower structures

Conference: ECITech 2022 - The 2022 International Conference on Electrical, Control and Information Technology
03/25/2022 - 03/27/2022 at Kunming, China

Proceedings: ECITech 2022

Pages: 5Language: englishTyp: PDF

Authors:
Ye, Xin; Guo, Jingfeng; Chen, Bijian; Fu, Xiaoxu; Xie, Ming (Fujian Yongfu Power Engineering Co., Ltd, Fuzhou, Fujian Province, China)

Abstract:
In order to reduce the corridor width occupied by the transmission line tower and make it economical, based on the 220kV line project of chentangzhuang power plant Yingfeng substation, through the comparison and selection of three different insulator string layout types and the selection of planning span, the "L-shaped insulator string" layout type and tower design parameters conducive to reducing the corridor width are obtained, which can provide reference for similar projects.